Moyola Park Football Club, Castledawson Moyola Park Football Club, Castledawson Moyola Park Football Club, Castledawson Moyola Park Football Club, Castledawson Moyola Park Football Club, Castledawson Moyola Park Football Club, Castledawson Moyola Park Football Club, Castledawson Moyola Park Football Club, Castledawson

Moyola Park Football Club, Castledawson

Sport and Leisure (Scroll down for more information)

Client Moyola Park Football Club
Architect McGurk Chartered Architects
Value £1.7M
Contract Period 62 weeks

Overview:

Built by Woodvale Construction, this project was for the provision of a full size FIFA 3rd generation artificial turf playing pitch, a new grass training pitch, the erection of a new clubhouse and changing facilities.

The development includes dugouts, pitch and ground perimeter fencing, car parking, a 200 seat covered accommodation stand and a pavilion with four team changing rooms, two officials' changing areas, an indoor multi sport area, a committee room and toilet facilities for spectators.

 

Key Facts:

  • The ground conditions were very challenging
  • This required the use of geotextiles and a large quantity of stone
  • A temporary access road was required through a neighbouring property – this required extensive stakeholder liaison
  • The project included for tree felling 
  • The electricity poles and overhead cables running across the site had to be relocated. These were put underground. This required meticulous planning and programme management due to the Health & Safety issues. 

 

Results:

Raymond Loughrey, Chairman of Moyola Park Football Club said: “It is a wonderful facility and we would like to thank all those who have helped us secure and build it.”