The Church of Our Lady Star of The Sea, Co. Donegal The Church of Our Lady Star of The Sea, Co. Donegal The Church of Our Lady Star of The Sea, Co. Donegal The Church of Our Lady Star of The Sea, Co. Donegal The Church of Our Lady Star of The Sea, Co. Donegal The Church of Our Lady Star of The Sea, Co. Donegal The Church of Our Lady Star of The Sea, Co. Donegal

The Church of Our Lady Star of The Sea, Co. Donegal

Restoration (Scroll down for more information)

Client Fr R Munster, St. Mary’s Church, Bundoran
Architect Mullarkey Pedersen Architects
Value £3.5m
Contract Period 88 weeks
Listed Building Reference Protected Structure

Overview:

This project was successfully delivered on a very complex and restricted site. The existing church, built in 1859, was successfully restored to its former glory, and while the attention was to retain the past of the old church, a new chapel was also constructed within the site boundary. This is a hexagonal shaped building, finished in cut stone with a natural slate and lead roof covering.

External works included for the construction of a new car-park, paving, access road, vehicular bridge, pedestrian bridge, drainage and the installation of new utility services.

The project was carefully phased to enable the church and the adjoining graveyard to remain open.

 

Key Facts:

  • The project was carried out over 4 phases. During Phase 1 the existing church and car park remained in use while the new chapel and bridges were under construction. During Phase 2 the existing church was refurbished within a very tight programme – 19 weeks. Phase 3 saw the completion of the new chapel extension after the existing church was re-opened. Phase 4 included for siteworks, including road realignment
  • We had to facilitate worship, weddings and funerals which operated smoothly as a result of daily liaison with the Parish Pries
  • Storage space and access was very restricted because of a river running through the site and the overlap with the public who required access to the church
  • We addressed these issues by careful planning, risk assessment, development of a detailed safe system of work and by involving the Parish Priest in all aspects of our planning and programming.

 

Results:

Ciaran Mullarkey, Mullarkey Pedersen Architects, stated: “Our experience of Woodvale Construction is that they are a first rate contractor who possess all of the abilities to complete a project on time, to budget and to the highest standard of workmanship. Their work force is extremely experienced and knowledgeable and is carefully managed by a team of excellent Site Agents and Contracts Managers. We found that they are particulary adept at working along with the design team in an inclusive and positive manner. They are proactive in problem solving – always looking for solutions instead of problems. The manner in which they controlled the site conditions at St. Mary’s Church (immediately adjacent to and over a fast flowing river) admirably demonstrated their respect for and control of Health 7 Safety. The experience of Woodvale Construction as main Contractor on this project has been totally successful. I welcome the opportunity to work with them again.”

This project was a Finalist in the 2010 RICS Awards for Building Conservation.